HOA BINH 5 WIND POWER – CONSTRUCTION TRANSPORTED BY NEXUS LOGISTICS

03/03/2022 22:10

Information about the project:
• Project name: Hoa Binh 5 Wind Power Plant - Phase 1
• Investor: Hacom Bac Lieu Energy Joint Stock Company
• Location: Vinh Thinh commune and Vinh Hau commune, Hoa Binh district, Bac Lieu province
• Area: 27.7 ha
• Capacity scale: 80MW
• Power output: 280,000 MWh/year
• Total investment capital: about 3,700 billion VND
• COD operation date: October 31, 2021

The wind power project is deployed and installed with 26 wind turbine towers with capacity from 3.0 to 3.3 MW/turbine over 140m high. Located on the premises with an area of ​​27.7 ha. The goal and mission of the project is to build and put the plant into use, connect to the national power grid on the 220 kV Gia Rai - Bac Lieu 2 line, using abundant wind energy as well as being environmentally friendly. environment to produce electric energy to provide for aquaculture as well as electricity for people in the area. Hoa Binh 5 Wind Power Plant project not only creates stable jobs for local people but also increases income for the local budget with a value of over 80 billion VND/year; Economic restructuring for the whole region in general and Bac Lieu province in particular.

With the responsibility of taking on the task of transporting wind power equipment for Hoa Binh 5 Wind Power project - Nexus Logistics has always made great efforts to ensure the quality of transportation in parallel with the construction progress as well as labor safety. for all employees. During the transportation of 26 wind turbines, initially encountered many difficulties and challenges in terms of moving terrain - stormy weather during construction as well as difficulties and limitations during the Covid-19 pandemic, but we was successfully surpassed by flexible improvements in transportation options throughout the process for peak productivity.


 

Each wind turbine pole is transported by high-quality super-heavy vehicles from the port yards through barges and to the wind power poles at the project for installation. Although it was built during the time of the Covid-19 epidemic, which severely affected many industries as well as the lives of Vietnamese people, Nexus Logistics successfully overcame the "Storm" of Covid 19 to complete the project successfully. and put it into use on schedule (October 31, 2021).Transporting wind power poles